Questions tagged [project-estimation]
2 questions
                    
                    1
                    
            vote
                
                2 answers
            
        Formula for PERT - Pessimistic time and optimistic time
I found PERT examples include a formula 
(a + 4m + b)/6
where a= optimistic time , b= pessimistic time and m= actual time to complete the task
but how to calculate a and b? 
please help me as soon as possible
        
        karthi
        
- 27
 - 1
 - 2
 - 4
 
                    1
                    
            vote
                
                2 answers
            
        What to look for in estimating a PowerBuilder Conversion Project?
I've been trying to do a spec for a PowerBuilder 9 to 11.5 
migration of a relatively complex application.  Granted PowerBuilder 
is not really my specialty I'm having issues trying to justify an 
estimate for this part of the project (and theā¦
        