I am working on a project plan where I have a resource available 1.5 hrs / day (so have set their "max. units" at 12.5% to represent this). Some of the tasks in the plan are over 1.5 hrs however (e.g. 3hrs), so when I try to do automatic resource leveling Project complains that 3hrs is > 1.5hrs and won't do it. What I want it to do is realize that the 3hr task will take two 1.5 hr days. I don't want to artificially break down 3hr tasks into two 1.5hr tasks either.

How do I get resource leveling to work like this?

SeanLabs
  • 175
  • 1
  • 1
  • 8

1 Answers1

0

Figured it out. Created a custom calendar with 1.5hrs/day for the resource & put max units back to 100%. Leveling then worked as expected.