In summary task information, Task type is set on " fixed duration" and is inactive (I can't change it). How can I change the duration?
Asked
Active
Viewed 58 times
1 Answers
0
In Auto Scheduled mode, the durations for Summary tasks are calculated based on the span of the subtasks. Since it is a calculated field the task Type is Fixed Duration.
In Manually Scheduled mode, the Summary task duration can be manually changed. In that case it is still a fixed duration.