MS Project tracks allocation of resources "daily". In other words MSP shows over-allocation or under-allocation of a resource on "per day" basis.
If you load a resource with 12h work on a 8h day then Resource Usage view shows it red. When you set the timescale of "Resource Usage" view to weeks, it still paints the week red even if only one day of the week is over-allocated and the rest of the week is completely empty.
I want to do task planning on a weekly basis and let everybody do their own planing for the week in their heads. As long as the workload on a resource for a week is not greater that 5d, there is no over-allocation for me and so that week is not be painted red.
Can this be done in MS Project?